MRPG is currently demolishing, reconstructing and upgrading the Scarsdale Drainage Pumping Station for Plaquemines Parish in Brathwaite, LA. This project is to be done in four separate phases to allow three of the four pumps running throughout the duration of the project. Scope includes removing all mechanical equipment from the existing station, constructing a reinforced concrete second floor, refurbishing and relocating the equipment upstairs, constructing a new structural steel metal building, and start-up of each pump one phase at a time.
HAZARD MITIGATION PLAN AT THE SCARSDALE DRAINAGE PUMPING STATION
Owner:
PLAQUEMINES PARISH GOVERNMENT
Contractor:
M.R. PITTMAN GROUP, LLC
Location:
PLAQUEMINES, LA
Contract Value:
$9,385,707